Monday 22 April 2013

New Building: Weeks 56-58

The most disruptive stage of the building work so far is now over—anyone visiting the church over the last few weeks can't have helped noticing the large trenches criss-crossing the yard outside. They are now all covered up, with the relevant pipes, drains and cables inside. There was a lot of soil to put back:

The library gallery has had its temporary barrier fitted. This will be in place until we raise the money for the library shelving. The permanent barrier will consist of lockable, swivelling bookshelves that will make the most of the space we have.

Here we have another glimpse of the new kitchen for the Parish centre.

And here is one of the bedrooms: painted and with all its electrical fittings, just awaiting the finishing touches.